The current stove will be replaced with a cooktop with a single oven built in below and a microwave above. The brick column (which covers the old stove pipe) will be demolished, and brick pavers will be installed in two columns, with a connecting arch above, to surround the cooktop area.


Week 0

After 2 days of demolition - Stove, cabinets, shelves gone

End of Week 1 - Transom is down

End of Week 2 - Brick tower is gone

End of Week 5 - New back door. New subfloor and joists. Electricals started

Week 12 - New tile floor. Cabinets installed

Week 14 - Countertops installed. Fabulous backsplash, mosaic and tile work! Appliances now functional.